Development & Evidence

Existing TRL 5 Evidence. TRL 6 Is the Next Stage.

OblinEngine has progressed through modelling, prototype construction, shallow hydraulic testing and deep-shaft testing. The technology is currently at TRL 5, with the next development stage being an integrated Australian demonstrator intended to progress the technology to TRL 6.

Current: TRL 5 Next Stage: TRL 6 Demonstration Deep-Shaft Testing Completed
Development Path

From Concept to TRL 5, Then to TRL 6

The development program has been staged to generate physical evidence, reduce technical uncertainty and progressively move the technology through successive readiness levels.

1

Concept Development

Initial modelling and system design established the proposed relationship between compressed-air injection, hydraulic uplift and recoverable water flow.

2

Shallow Testing

Controlled prototype testing measured air input, water movement and hydraulic head under shallow experimental conditions.

3

Deep-Shaft Testing

Testing at approximately 92.5 metres provided evidence that the hydraulic uplift mechanism remained effective at substantially greater depth.

4

TRL 6 Demonstrator

The next stage is an integrated Australian demonstration intended to generate system-level evidence required for progression from TRL 5 to TRL 6.

Technology Readiness

Current: TRL 5. Next: TRL 6.

Current TRL 5 Position

The existing development position is supported by completed physical testing of the core hydraulic uplift mechanism.

  • Proof-of-concept development completed
  • Shallow hydraulic testing completed
  • Deep-shaft testing completed
  • Testing conducted to approximately 92.5 m depth
  • Hydraulic head demonstrated during deep testing
  • Physical engineering evidence generated

Next TRL 6 Stage

The proposed Australian demonstrator will integrate the major system components and measure performance across the full energy pathway.

  • Integrated compressor-to-generator operation
  • Representative-depth system testing
  • Electrical input and output measurement
  • Auxiliary-load measurement
  • Repeatability testing
  • Integrated energy-performance assessment
  • Independent technical assessment
Development pathway: TRL 5 is the established starting point. The proposed Australian integrated demonstrator is the next development stage intended to generate the evidence required for progression to TRL 6.
Measured TRL 5 Evidence

Physical Results Generated to Date

The existing TRL 5 position is based on completed physical testing, not solely on modelling or theoretical analysis.

92.5 m Approximate depth of completed deep-shaft testing
2.4 m Approximate hydraulic head demonstrated during deep testing
8.36:1 Approximate measured water-to-air flow relationship during shallow testing at approximately 175 mm hydraulic head
Evidence discipline: these figures are results from completed development testing. They form part of the existing TRL 5 evidence base and are not represented as guaranteed commercial-system performance.
Shallow Testing

Establishing the Hydraulic Mechanism

Early physical testing examined whether controlled compressed-air injection could generate measurable water uplift and hydraulic head.

The tests investigated the relationship between injected air, water flow, bubble behaviour and resulting hydraulic head under controlled conditions.

One measured result from the shallow program was an approximate water-to-air flow relationship of 8.36:1 at approximately 175 mm hydraulic head.

Purpose of the shallow program

Demonstrate the underlying mechanism, establish measurement methods and generate evidence to support progression to deeper testing.

Air bubbles rising through water representing OblinEngine shallow hydraulic testing

Illustrative two-phase air-water flow image. It is not presented as a photograph of the measured shallow test.

Deep-Shaft Testing

Physical Testing at Approximately 92.5 Metres

The next major development step was deep-shaft testing at approximately 92.5 metres.

The purpose was to determine whether the hydraulic uplift mechanism remained observable under materially greater water-column depth and injection pressure.

Approximately 2.4 metres of hydraulic head was demonstrated during the deep test.

This testing provided further physical evidence supporting the current TRL 5 position and progression toward an integrated TRL 6 demonstrator.

What the deep test established: the hydraulic uplift mechanism remained observable at substantially greater depth, providing evidence for progression to the next development stage.
Deep vertical shaft engineering concept representing OblinEngine deep-shaft testing

Conceptual shaft visualisation, not a photograph of the completed 92.5 m test installation.

Next Development Stage

What Must Be Added to Progress from TRL 5 to TRL 6

The TRL 6 project must move beyond subsystem evidence and demonstrate the integrated system under representative operating conditions.

System Integration

Operate the compressor, air-delivery system, uplift shaft, hydraulic circuit and turbine-generator as one integrated system.

Energy Measurement

Measure electrical input, electrical output and auxiliary consumption across defined operating conditions.

Hydraulic Measurement

Measure air flow, pressure, water flow and hydraulic head throughout representative test runs.

Repeatability

Determine whether observed system performance can be reproduced across multiple operating cycles and defined conditions.

Control & Stability

Characterise operating behaviour, system stability and the control requirements of the integrated demonstrator.

Independent Assessment

Generate evidence suitable for external technical review of whether progression from TRL 5 to TRL 6 is justified.

Instrumentation

Moving from TRL 5 Evidence to Integrated TRL 6 Data

The proposed demonstrator is intended to measure the major electrical, pneumatic and hydraulic variables needed to assess system performance.

  • Compressor electrical input
  • Auxiliary electrical consumption
  • Air pressure
  • Air flow
  • Water flow rate
  • Hydraulic head
  • Turbine-generator electrical output
  • Operating duration and stability
  • Repeatability
  • Control-system and fault data

Where the final test configuration provides a valid complete charge-discharge measurement boundary, the project is also intended to determine round-trip efficiency.

Engineering monitoring and data logging representing the OblinEngine TRL 6 demonstrator
Independent Assessment

TRL 6 Must Be Supported by the Evidence

OblinEngine is not represented as already being at TRL 6.

Independent technical assessment is intended to examine the demonstrator methodology, instrumentation, recorded data, repeatability and resulting performance evidence.

The purpose is to determine whether the integrated results support progression from the existing TRL 5 position to TRL 6.

Technology-readiness discipline: TRL 5 is the current development position. TRL 6 is the objective of the next integrated Australian demonstration.
Engineering instrumentation representing independent technical assessment of OblinEngine
Evidence Transparency

Measured Results and Future Targets Are Kept Separate

The development program distinguishes clearly between what has already been demonstrated at TRL 5 and what remains to be demonstrated at TRL 6.

Already Demonstrated

  • Hydraulic uplift mechanism
  • Shallow physical testing
  • Deep-shaft physical testing
  • Hydraulic head generation at depth
  • Existing TRL 5 evidence base

Still to Be Demonstrated

  • Integrated system operation
  • Net electrical performance
  • Auxiliary consumption
  • Repeatability
  • Integrated energy performance
  • Round-trip efficiency where measurable
  • Independent TRL 6 assessment
Next Development Stage

TRL 5 Established. TRL 6 Is Next.

The proposed Australian integrated demonstrator is intended to generate the measured system-level evidence required to progress OblinEngine from TRL 5 to TRL 6.